First interconnector will be switched off today for works to resume on the next phase of IC2

First interconnector will be switched off today for works to resume on the next phase of IC2

Tvmnews.Mt • October 27, 2026

Work on Malta’s second electricity interconnector (IC2) has reached another major milestone, with significant progress registered at the Ragusa Substation in Sicily – a key step in delivering one of the country’s most important energy infrastructure projects.

During the recent planned shutdown of IC1, engineers completed the trenches that will house the cables linking the new hybrid switchgear to the 220 kV reactor. They also carried out extensive modifications and installations to the high‑voltage infrastructure on site.

Once IC1 was safely brought back online, Terna Energy Solutions proceeded with the assembly and installation of the new air‑insulated switchgear for IC2. This ensured that critical works could continue without interrupting the operation of Malta’s existing interconnector.

With most preparatory works now finalised, the project is entering its phase with full electrical integration, bringing Malta closer to securing a more resilient and diversified energy supply. It will involve the connection of the new 220kV reactor with the hybrid switchgear through high voltage cables which will be placed in trenches, completed during the switch off of the IC1.

Heavy construction machinery and specialised lifting and cable‑pulling equipment will be deployed at the Ragusa Terminal Station in the coming days, as the IC2 project enters a new phase of technical integration.

To safeguard workers and protect existing high‑voltage infrastructure, temporary operational measures will be introduced. As part of these precautions, IC1 will be switched off once again for approximately eight days starting on 27 October.

The planned works mark another significant milestone in integrating Malta’s second electricity interconnector within Enemalta’s Ragusa facilities. Enemalta said it is working in close coordination with Interconnect Malta, Terna Energy Solutions and Italy’s Transmission System Operator to ensure the operations proceed safely and efficiently.

Enemalta has implemented the necessary operational measures to ensure Malta’s electricity demand can be fully met through local generation while critical works linked to the IC2 project continue.

Executive Chairman Ryan Fava said the second interconnector, together with Enemalta’s broader investment programme, including the newly inaugurated distribution centres, demonstrates the corporation’s ongoing commitment to strengthening Malta’s energy infrastructure and delivering a more resilient and reliable network for both Malta and Gozo.

Interconnect Malta’s Executive Director, Steve Farrugia, noted that the latest progress in Ragusa reflects the extensive planning, coordination and technical expertise required for a strategic project of this magnitude. He said the achievements so far underline the importance of collaboration between Enemalta, Interconnect Malta, Terna Energy Solutions and Italy’s Transmission System Operator.

Following the completion of the current works, installation, integration and testing will continue at the Ragusa Terminal Station as the final steps before Malta’s second interconnector enters its commissioning phase later year.

IC2 is a cornerstone of the Government’s long‑term energy strategy. The new link will substantially reinforce Malta’s electricity security and create the conditions for wider integration of renewable energy sources into the national grid.

The project is co‑financed by the European Union through the European Regional Development Fund (ERDF), supporting Malta’s drive to build an energy system that is more resilient, more sustainable and better prepared for future demand.

The €300 million IC2 project will deliver a new 122‑kilometre electricity interconnection between Malta and Sicily, featuring a 225 MW capacity and a 245 kV HVAC submarine cable linking the Magħtab terminal to Ragusa. The new link will run parallel to Malta’s current interconnector, commissioned in 2015, but positioned at a safe distance to ensure operational security and long‑term reliability.