IC1 to shut down for eight days as works on second interconnector advance

IC1 to shut down for eight days as works on second interconnector advance

Maltatoday.Mt • October 26, 2026

Interconnector IC1 is planned to be shut down for eight days, from 27 October, to allow work on the second interconnector (IC2) at the Ragusa Substation in Sicily.

The works involve connecting a newly installed 220kV reactor to the hybrid switchgear module with high-voltage cables. The IC1 will be taken out of service to keep personnel and existing infrastructure safe whilst heavy construction machinery and specialised lifting and cable-pulling equipment operate within the terminal station.

The cables will run through trenches completed during a IC1 shutdown, when the existing link was also taken offline. Since IC1 returned to service, Terna Energy Solutions has continued assembling and installing the new IC2 air-insulated switchgear.

The work is being coordinated between Enemalta, Interconnect Malta, Terna Energy Solutions and the Italian Transmission System Operator.

The second interconnector, known as IC2, is designed to double Malta’s electricity interconnection capacity. The first link, which Enemalta commissioned in 2015, connected Malta directly to the European electricity grid.

The latest works come as the second link moves closer to completion and electricity demand continues to rise.

At the beginning of October, Interconnector IC1 was set to face a 12-day shutdown to support works at Ragusa for the second interconnector, which is moving closer to completion

At the terminal station, installation, integration and testing will continue once the cables are connected, with commissioning planned for later year.

IC2 will be a new 225MW cable 122km long, running from Maghtab in Malta to Ragusa. It will be laid parallel to the existing link, commissioned in 2015, but at a safe distance.

The €300 million project is co-financed by the European Union through the European Regional Development Fund. According to its cost-benefit analysis, it will cut 13.5 million tonnes of CO2 emissions.

Once completed, the 245kV submarine cable will double Malta's connectivity to the European energy grid. The project is also meant to strengthen security of supply and help Malta absorb more renewable energy, such as offshore wind and solar.

Executive chairman Ryan Fava said Enemalta had made the necessary preparations to "meet the country's electricity requirements through local generation throughout this temporary shutdown".

Interconnect Malta executive director Steve Farrugia said the completion of the preparatory works and the installation of major equipment now allowed the project to proceed with the phase of electrical integration, "bringing the project another step closer to completion".