Back Biz.Chosun LS Cable to supply 700 billion won in cables for New York power grid
LS Cable & System is accelerating its extra-high-voltage power grid business in New York.
LS Cable & System said on the 23rd that its U.S. subsidiary, LS Cable Systems America, will supply approximately 700 billion won worth of 345-kilovolt (kV) extra-high-voltage submarine and underground cables for the Propel NY Energy project in New York.
The project, jointly led by the New York Power Authority (NYPA) and transmission grid developer and operator New York Transco, will build approximately 145 kilometers of power lines connecting Long Island, the New York City boroughs of Queens and the Bronx, and Westchester County. The project aims to expand transmission capacity, stabilize the power supply and connect renewable energy sources, including offshore wind power.
Construction will begin in earnest after New York state authorities recently approved the construction plan, following the signing of a contract in February. LS Cable & System will supply 345 kV-class underground and submarine extra-high-voltage cables, carry out electrical work and conduct completion tests for the project.
LS Cable & System is also strengthening its North American operations. The company is developing LS GreenLink, now under construction in Virginia, into a production hub for extra-high-voltage submarine cables. Meanwhile, Gaon Cable is increasing its supply of distribution cables and bus ducts for artificial intelligence data centers (AIDC) and renewable energy projects through its U.S. subsidiary, LSCUS, with related sales growing rapidly.
The company is also expanding its submarine cable installation capacity. LS Marine Solution is building a 19,000-ton-class cable-laying vessel, with the aim of putting it into service in 2028. LS Cable & System plans to use the vessel to strengthen its capacity to deliver turnkey projects spanning production and installation.
An LS Cable & System official said, "In Korea, large-scale national power grid projects, including the West Coast Energy Highway, are being pursued as renewable energy expands and demand for electricity grows. For projects that integrate long-distance submarine and land-based transmission networks, the ability to manage both the supply and installation of extra-high-voltage underground and submarine cables is a key competitive advantage. We will build on that capability to actively participate in domestic -generation power grid projects as well."
The full story
This article is one source in a clustered incident — the cluster page carries the summary, timeline and every other outlet covering it.