- •Meta says it is re-evaluating its 2030 net-zero goal and interim milestones and has not committed to a new timeline.
- •Meta reports 2025 net emissions of 11.8 million metric tons of CO2, up 45% year over year.
- •Meta's electricity consumption reportedly rose 35% year over year as data centers came online.
- •Meta left the RE100 renewable energy initiative in July, citing the group's stricter reporting requirements.
- •The Hyperion data center in Louisiana, which relies on natural gas, is central to the emissions increase.
Meta's 2026 sustainability report says the company is re-evaluating its 2030 net-zero emissions goal and near-term intensity targets, and has not committed to a new timeline. A Meta spokesperson told TechCrunch the company remains committed to net zero but is re-evaluating the 2030 timeline and interim milestone. CNET reports Meta's 2025 net emissions were 11.8 million metric tons of CO2, a 45% year-over-year increase per the company. Electricity consumption reportedly rose 35% year over year as additional data centers came online, according to the report. TechCrunch notes Meta's greenhouse gas emissions have more than doubled over four years and that its data center emissions rose more than 12-fold between 2024 and 2025, a figure TechCrunch attributes to the company's emissions accounting. Both outlets link the shift to AI infrastructure demand, including the Hyperion data center in Louisiana, which is planned to bring about two gigawatts of capacity online around 2030 and relies on natural gas. Meta left the RE100 renewable energy initiative in July, per TechCrunch, after RE100 introduced more rigorous reporting requirements. Meta's stated rationale is that AI infrastructure demand grew faster than projected. TechCrunch argues the company's AI investment was a conscious choice. CNET notes similar goal rollbacks at Microsoft, Amazon and Google.
Ask AI about this cluster
Answers cite the sources they use
Timeline
More articles in this cluster (3)
Following this threat?
Track Amazon in your own feed — you're alerted when they show up in new reporting, leak sites or exploitation.
Free account · no card needed
Common questions
How much did Meta's emissions change in 2025?
Has Meta set a new net-zero deadline?
Why are emissions rising?
Continue Reading
CVE-2026-123890: Auth bypass in VMware vCenter exploited by Armory Castle before patch CVE-2026-123890, a flaw in VMware vCenter Server rated CVSS 9.8, allows an unauthenticated remote attacker to obtain an administrator session on the platform. According to the Google Threat Intelligence Group, the flaw was exploited by the espionage group Armory Castle (formerly UNC5221), which has suspected China…