Talkofthesound NY Regulators Approve First Propel NY Energy Construction Plans; New Rochelle Timing Unclear
Article Content
- •NY PSC approved the first two Propel NY Energy EM&CPs on Nov. 19, 2026, covering Phase 1 and Phase 2 work.
- •Horizontal directional drilling at Hudson Park in New Rochelle may affect parking, beach, marina and nearby streets.
- •Reported drilling windows conflict: the Phase 2 fact sheet lists Nov 2026 to Apr 2027, while the announcement points to early-year start and mid-2027 activity.
- •The project is a four-year build with completion targeted for 2030, and additional construction approvals are still pending.
- •This is an infrastructure construction story with no cybersecurity threat, CVEs or indicators of compromise.
The New York State Public Service Commission approved the first two Environmental Management and Construction Plans (EM&CPs) for Propel NY Energy on Nov. 19, 2026. The approximately 90-mile underground and submarine transmission project, developed by New York Transco and the New York Power Authority, will run between Long Island, Queens, the Bronx and Westchester County. The approved Phase 2 plan covers horizontal directional drilling at Hudson Park and Beach in New Rochelle and Shore Road in Oyster Bay, Long Island, to prepare shoreline cable connections. The Crossing Group was selected for the drilling, with Hallen Integrated Construction Services, while LS Cable & System and Taihan were selected to supply cables. Construction is expected to take about four years, with completion scheduled for 2030. Per the companies, the project will support an estimated 2,000 jobs annually and an estimated $2.4 billion in economic benefit. Talk of the Sound reports that the project's Phase 2 fact sheet lists drilling windows of November 2026 to April 2027 and November 2027 to April 2028, while the Nov. 20 announcement says initial construction begins early in the year with more active work in mid-2027, leaving the New Rochelle schedule unclear. Additional approvals are still required for transition vaults, submarine cables and other system portions. Talk of the Sound has asked New York Transco to clarify the timing.
Ask AI about this cluster
Answers cite the sources they use
Timeline
More articles in this cluster (2)
Following this threat?
Track Hallen Integrated Construction Services in your own feed — you're alerted when they show up in new reporting, leak sites or exploitation.
Free account · no card needed
Common questions
Does this affect New Rochelle residents?
Is any cybersecurity threat involved?
What approvals remain outstanding?
Continue Reading
CVE-2026-123890: Auth bypass in VMware vCenter exploited by Armory Castle before patch CVE-2026-123890, a flaw in VMware vCenter Server rated CVSS 9.8, allows an unauthenticated remote attacker to obtain an administrator session on the platform. According to the Google Threat Intelligence Group, the flaw was exploited by the espionage group Armory Castle (formerly UNC5221), which has suspected China…