  • •Decommissioning offshore cables is technically feasible according to TenneT and NKT.
  • •Economic viability of decommissioning varies by project, influenced by material value and local conditions.
  • •Early planning for cable decommissioning is recommended to promote sustainability.

TenneT and NKT have completed a joint study confirming that decommissioning offshore power cables is technically feasible and could aid in recycling and reducing carbon emissions. The study analyzed various aspects including environmental impact, logistics, and regulatory requirements. It emphasized that while the technical aspects are manageable, the economic viability of decommissioning projects varies based on factors like material value and local market conditions. The companies recommend early planning for decommissioning to ensure sustainable practices in future offshore projects. The study's findings were supported by a team of trainees from TenneT and specialists from both organizations. No immediate cybersecurity threats or vulnerabilities were reported in relation to this study.

Start a free Starter trial for enhanced analysis

Ask AI about this cluster

Updated 23d ago How this analysis works

Timeline

2026-10-19
Study on offshore cable decommissioning published
TenneT and NKT released findings on the feasibility of decommissioning offshore cables, focusing on technical, environmental, and economic aspects.
Inspenet
2026-10-22
Study findings reported by Oedigital
Oedigital reported on the joint study by TenneT and NKT, highlighting the importance of early planning for offshore cable decommissioning.
Oedigital

More articles in this cluster (3)

Following this threat?

Track NKT in your own feed — you're alerted when they show up in new reporting, leak sites or exploitation.

Free account · no card needed

Common questions

What does the study conclude about offshore cable decommissioning?
The study concludes that decommissioning offshore cables is technically feasible and can support recycling and CO2 reduction.
What factors influence the economic viability of decommissioning?
Economic viability is influenced by material value, processing costs, and local market conditions.
What is recommended for future offshore projects?
The study recommends considering decommissioning needs from the earliest stages of project development.