Back Talkofthesound State Approves Propel NY Energy Construction Plans, but New Rochelle Start Date Remains Unclear
NEW ROCHELLE, NY (November 20, 2026) — State regulators have approved the first two construction plans for Propel NY Energy, a major electric transmission project that will bring high-voltage power cables beneath Long Island Sound and through New Rochelle, setting the stage for construction that could affect Hudson Park, local streets and waterfront recreational facilities.
The New York State Public Service Commission approved the plans Nov. 19, clearing another regulatory hurdle for the approximately 90-mile underground and submarine transmission project being developed by New York Transco and the New York Power Authority. The companies announced the approvals and the selection of several major construction contractors in a Nov. 20 news release.
The project will strengthen electrical connections between Long Island, New York City and Westchester County , increasing the capacity and reliability of the regional power grid. Construction is expected to take approximately four years, with the transmission system scheduled for completion in 2030.
The second approved Environmental Management and Construction Plan covers horizontal directional drilling at Hudson Park and Beach in New Rochelle and Shore Road in the Town of Oyster Bay on Long Island. The drilling will prepare the shoreline connections for submarine cables that will cross Long Island Sound between New Rochelle and Glen Head.
The project’s New Rochelle landfall will be located at the Hudson Park and Beach parking lot, where underground transition vaults will eventually connect the submarine cables to underground transmission lines extending through the city. The first two construction approvals do not cover all the work required to complete the project. Additional plans must be approved for installation of the transition vaults, submarine cables and other portions of the transmission system.
The Crossing Group has been selected to perform the horizontal directional drilling for the New Rochelle-to-Glen Head submarine crossing. The company will work with Hallen Integrated Construction Services, while LS Cable & System will supply and install the submarine cables. LS Cable & System and Taihan have also been selected to supply underground transmission cables.
For New Rochelle residents, one immediate question is when construction will begin and how it will affect access to Hudson Park, the beach, marina and surrounding streets.
The project’s Phase 2 fact sheet identifies two construction windows for horizontal directional drilling at Hudson Park, from November 2026 through April 2027 and again from November 2027 through April 2028. However, the Nov. 20 announcement says initial construction is anticipated to begin early year, with more active construction expected in mid-2027.
The discrepancy leaves the timing of work in New Rochelle unclear. Talk of the Sound has asked New York Transco to clarify whether the schedule has changed and when residents should expect construction activity at Hudson Park.
The approved Phase 2 plan addresses temporary construction areas, equipment staging, truck traffic, lighting, noise mitigation and environmental protections associated with drilling operations. It does not establish in the publicly released fact sheet how many parking spaces might be unavailable, whether beach or marina access will be restricted, or how long particular disruptions might last.
Construction also has financial implications for New Rochelle. In October, the City Council approved accepting a $430,000 advance payment from NYPA for easement interests at Hudson Park and Beach while preserving the city’s right to seek additional compensation.
The city’s proposed 2027 budget separately projects $4.3 million in easement revenue for 2026, compared with $40,000 proposed for 2027. Corporation Counsel has said most of the projected 2026 easement revenue is associated with Propel NY Energy, although the budget does not identify the amount attributable to the project. Questions remain the total compensation New Rochelle will receive and the agreements governing the use and restoration of city property.
The importance of the transmission project was underscored by a Nov. 17 report from the New York Independent System Operator, which oversees the state’s electric grid. The 2026 Reliability Needs Assessment concluded that Propel NY Energy will provide substantial reliability benefits to Long Island and the statewide electric system.
According to NYISO, without Propel NY Energy, Long Island could experience transmission reliability deficiencies as early as summer 2030. The report also found that without the project, a projected statewide electricity resource deficiency would occur one year earlier and be approximately 550 megawatts larger.
The findings provide independent support for the project’s importance to the regional power grid, although NYISO also concluded that additional electricity generation and other resources will be needed to address future statewide reliability concerns. The report assumes Propel NY Energy will enter service by May 2030.
The project developers estimate that construction across the entire route will support approximately 2,000 jobs annually and generate $2.4 billion in regional economic activity. Those estimates apply to the overall project, rather than New Rochelle specifically.
“Propel NY Energy will deliver a more reliable energy future for New York while creating meaningful economic opportunities for communities along the project route,” said Joris Veldhoven, president of New York Transco.
Veldhoven said the recent regulatory approvals and contractor selections demonstrate that the project is ready to move toward construction. NYPA President and CEO Justin E. Driscoll said the companies are working with local communities and contractors to complete the project safely and on schedule.
As construction approaches, New York Transco and NYPA say they are expanding public communication efforts, including a redesigned project website with an interactive construction map, an online inquiry form and a planned 24-hour staffed telephone hotline.
The quarterly public webinar is scheduled for Dec. 15 at 6 p.m. , when project representatives are expected to provide updates, answer questions and explain the new public information tools.
Talk of the Sound has contacted New York Transco seeking detailed New Rochelle construction maps, updated schedules, information road closures and park access, copies of city agreements and notification of future community meetings. The publication has also requested information how residents and local news organizations can receive timely construction alerts.
The project is being reviewed by the Public Service Commission under Case No. 24-T-0446. Additional information and project documents are available at
This article was prepared with the assistance of AI tools under the direction and editing of Robert Cox.